The well is finished
A first big step could be achieved with our borehole completion. This borehole will provide the students with drinking water once the school is opened. Furthermore it already means an assistance at the work site, because now no water e.g. for the concrete has to be delivered costly.
When we began drilling in November, the excitement was big if we will hit water. But then the reliefing news came: The drilling was a success and the workers actually hit water. In fact they had to dig 100 metres, but nevertheless it was big luck, because thus it saved us the costs and efforts of another drilling. The borehole instantly was mounted, which means, that a pipe was laid and a casing pump was connected. Besides a generator and a polytank with stand will be acquired. In total the costs added up to 6000 EUR, which could be covered up with the generous donations and the successful charity events of the last year.
We are pleased that the building of the school is going forward step by step and we count on further help from your side.
Two workers connecting the pump.